I'm sharing this technical support case

REQUEST
Can I change references to the estimate/BoQ file when working with my Construction cost management file

ANSWER
The CCE document isn't directly linked to any external file.

The 'Assisted document creation (SuperWizard)' feature, is only way of speeding up the process to create your Construction Cost estimate document; once created, by importing the relevant data from an Estimate file, all references are lost.