Forum

Helping others, engage in discussions, share your experiences and knowledge with other users.

Antony

How to change the references to the BoQ file in a construction cost estimating document

Antony 2018-09-04 16:35:19


I'm sharing this technical support case

REQUEST
Can I change references to the estimate/BoQ file when working with my Construction cost management file

ANSWER
The CCE document isn't directly linked to any external file.

The 'Assisted document creation (SuperWizard)' feature, is only way of speeding up the process to create your Construction Cost estimate document; once created, by importing the relevant data from an Estimate file, all references are lost.